Broken Arrow Drainage Advisory Committee
Meeting of: 07-28-2025
Title:
title
Consideration, discussion and possible action to recommend to City Council to expend funds for drainage improvements adjacent to the Millicent Pond II Subdivision (Case No. 25-011)
End
Background:
The proposed project is to investigate and design improvements to a drainage swale on private property that flows into the City’s public infrastructure in the Millicent Pond II subdivision. The swale collects approximately 20 acres of offsite flow and drains to existing area inlets located in drainage easements. The swales are not in drainage easements. The swale has not been maintained and has filled in over the years and therefore capacity of the swale has been lost. The runoff comes out of the banks during substantial rainfall events and is causing adverse impacts to multiple property owners along S. Joshua Ave.
This is in the Haikey Creek Watershed.
Staff is requesting $15,000.00 of the 2018 General Obligation Bond Proposition 6 funds for survey funds to conduct an in-house design and possible in house construction to mitigate the offsite flow.
Cost: $15,000.00
Funding Source: 2018 General Obligation Bond, Proposition 6
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Drainage Report, Exhibits
Recommendation:
recommend
Recommend to Council the expenditure of funds for drainage improvements adjacent to the Millicent Pond II Subdivision (Case No. 25-011)
end