Broken Arrow City Council
Meeting of: 10-07-2025
Title:
title
Approval of and authorization to award to the lowest responsible bidder, Cherokee Pride Construction Inc., a construction contract for the Ridgeway Heights Residential Streets Concrete Panel Replacement, a project located northeast of Kenosha Street and Midway Road (Project No. ST24080)
End
Background:
The Engineering and Construction Department staff worked with a design consultant to prepare design plans for residential street rehabilitation within the Ridgeway Heights I, II and III subdivisions. The plans were completed and consist of residential street repair, of approximately 10,300 square yards of full depth concrete pavement removal and replacement as well as approximately 1,400 square yards of concrete pavement patching. Additional miscellaneous work also included are replacement of approximately: 460 lineal feet curb and gutter, 200 square yards of portland cement concrete sidewalk and 120 square yard of portland cement concrete driveway improvements.
The project was advertised on August 25 and September 1, 2025. Bids were opened on September 16, 2025 with three (3) bids received, all of which being responsive. A certified bid tabulation is attached. The bids submitted were composed of thirteen (13) pay items to form the total base bid. The lowest responsible bidder Cherokee Pride Construction Inc. with a total bid of $1,321,566. The total engineer’s estimate for this project was $1,385,899.
Cost: $1,321,566.00
Funding Source: 2018 GO Bond Proposition 1
Requested By: Charlie Bright, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Certified Bid Tabulation
Recommendation:
recommend
Approve and authorize award to the lowest responsible bidder, Cherokee Pride Construction Inc., a construction contract for the Ridgeway Heights Streets Concrete Panel Replacement project (Project No. ST24080)
end