Title: Approval of and authorization to execute Change Order No. 1 with Cherokee Pride Construction, Inc. for the College Addition Phase 1 (ST24170)
Attachments: 1. College_Addition_Final_Change_Order
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 03-24-2026

 

Title:

title

Approval of and authorization to execute Change Order No. 1 with Cherokee Pride Construction, Inc. for the College Addition Phase 1 (ST24170)

End

 

Background:

 The College Addition Phase 1 Residential Streets Asphalt Repair and Resurfacing project is to rehabilitate the streets in the old town part of the Rose district in Broken Arrow.    

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     The overage and underrun bid items identified demonstrate that the final quantity change order is base on the actual quantities placed in the field. Additional curb and gutter were added on 3rd street between E. Freeport Street and E. Elgin Street, as there was no existing curb on either side of the roadway from the alley to the north. This work also included construction of two alley drive approaches and full-depth roadway patches measuring 24 feet by 30 feet and 12 feet by 30 feet due to roadway base failures. 

Total time added to contract is:

-                     0 Days

 

 The total cost for Change Order #1 amounts to $7,939.42

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $7,939.42

Total Cost of Change Orders:                                          $7,939.42

Original Contract Amount:                                          $573,292.00

Revised Contract Amount:                                          $581,231.42

 

Percent Change in Contract:                                          1.38% ( Max 15%)

Applicable to Comp. Bid Act:                     0.0%

Cost:                                                                $7,939.42

Funding Source:                     2018 GO Bond, CDBG

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Change Order 1 College Addition Final Change Order  

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction. INC for the College Addition Phase 1 (ST24170)