File #: 25-743    Name:
Type: Consent Item Status: Agenda Ready
File created: 5/20/2025 In control: Broken Arrow City Council
On agenda: 6/2/2025 Final action:
Title: Approval of and authorization to execute Agreement for Professional Consultant Services with Walter P. Moore and Associates, Inc. for the 245th E. Avenue Improvements from Kenosha Street to Oakland Street (Project Number 2552200)
Attachments: 1. AE Agreement - 2552200 - 245th Impr w summ legal signed
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 06-02-2025

Title:
title
Approval of and authorization to execute Agreement for Professional Consultant Services with Walter P. Moore and Associates, Inc. for the 245th E. Avenue Improvements from Kenosha Street to Oakland Street (Project Number 2552200)

End

Background:
Due to deterioration of existing infrastructure over time and also from recent development construction activities, approximately 1,500 feet of 245th E. Avenue from Kenosha Street to the north is in need of significant rehabilitation. Engineering & Construction Department staff has negotiated an Agreement for Professional Consultant Services with Walter P. Moore and Associates, Inc. to provide design services for said roadway improvements as well as upgrade existing waterline in the same vicinity.
The project scope includes widening and full depth reconstruction of the existing narrow two-lane roadway to a two-lane asphalt roadway, minimum 22' in width, with sod shoulders and improved open drainage ditches. Also included in the scope are improvements of existing waterline along S. 245th E. Avenue, approximately 1,500 L.F. in length, from Kenosha tying into existing waterline at Oakland Street. The project also includes other miscellaneous improvements such as: drives, storm drains under drives, roadway cross drains, ditch grading, miscellaneous appurtenances, identification of the need for utility relocations as well as all governmental agency coordination/permitting. It is anticipated improvements will not require additional right-of-way therefore services for right-of-way acquisition are not included in this agreement.
Staff recommends approval of this agreement.

Cost: $119,000.00
Funding Source: Engineering Operational Budget
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager's Office
Attachments: Agreement for Professional Consultant Services

Recommendation:
recommend
Approve and ...

Click here for full text