Approval of and authorization to execute Change Order No. 4 with Ascend Commercial Builders for the Broken Arrow Public Works Field Office Project (2217090)
End
Background:
The BA Public Works Field Office project is to renovate the building for field services personnel
Change Order #4 addresses the following additions/deletions/changes to the contract:
- Change to contingency amount. The credits for removal of plywood, removal of fence, and the removal of data from the contract will now be added to the built-in contingency for the project.
The total cost for Change Order #4 amounts to ($29,027.00)
The additional cost associated with these changes is as follows:
Previous Change Orders: $131,173.86
This Change Order(s): $(29,027.00)
Total Cost of Change Orders: $102,146.86
Original Contract Amount: $1,700,314.98
Revised Contract Amount: $1,802,461.84
Percent Change in Contract: 7.71%
Applicable to Comp. Bid Act: 0%
Cost: ($29,027.00)
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: BA Public Works Field Office Change Order 4
Recommendation:
recommend
Approve and authorize execution of Change Order #4 with Ascend Commercial Builders for the BA Public Works Field Office Project (2217090)