Approval of and authorization of Final Acceptance for the public improvements at Creekside at Forest Ridge Phase 2 located at 7200 East Kenosha Street
End
Background:
BR Heavy Construction, LLC has completed the construction for Creekside at Forest Ridge 2 located project. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvements are for the water, sanitary sewer, storm sewer, and paving installations.
The owner desires to donate the public improvements identified above to the City of Broken Arrow. These improvements have an approximate value of $1,018,453.00
Cost: None
Funding Source: N/A
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Infrastructure Inventory - Creekside at Forest Ridge Phase 2
Recommendation:
recommend
Approve and authorize final acceptance and donation of the public improvements at Creekside at Forest Ridge Phase 2 located at 7200 East Kenosha Street