Broken Arrow City Council
Meeting of: 8-3-2026
Title:
title
Consideration, discussion and possible approval of award to the lowest responsible bidder, Cherokee Pride Construction, Inc., and authorization to execute a construction contract for ST2031 - Aspen Avenue Improvements from Jasper Street to Tucson Street (Phase 3)
End
Background:
The project is a 2018 GO Bond Proposition 1 project and was designed by CEC for construction including rehabilitation and widening of the existing paving to five (5) lanes on Aspen Avenue from Jasper Street north to the Tucson Street intersection. The project also includes construction of sidewalk, concrete work at driveway returns, storm sewer, waterline and new signage, striping and pavement markings on Aspen Avenue from Jasper Street to Tucson Street.
The project was advertised on July 7, 2026. Bids were opened on July 28th, 2026 with six (6) bids received and all being responsive. The Certified Bid Tabulation is attached. The bids submitted were composed of one-hundred and eight (108) pay items to form the Total Base Bid. The lowest responsible bidder was Cherokee Pride Construction, Inc., with a Total Bid of $4,781,011.15. The engineer’s estimate for improvement of this mile of arterial street was $6,425,832.00.
Cost: $4,781,011.15
Funding Source: 2018 GO Bond - Proposition 1
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Certified Bid Tabulation
Recommendation:
recommend
Approve award to the lowest responsible bidder, Cherokee Pride Construction, Inc., and authorize execution of a construction contract for ST2031 - Aspen Avenue Improvements from Jasper Street to Tucson Street (Phase 3)