Broken Arrow Municipal Authority
Meeting of: 08-05-2024
Title:
title
Approval of and authorization to execute Amendment No. 2 to Professional Consulting Agreement with Native Strategies, LLC for the Omaha Waterline Improvements Project (Project No. WL22010)
End
Background:
This project is for the relocation of the Omaha Waterline located along Omaha Street (E. 51st St. S.) between Elm Place and 23rd Street. The waterline is being relocated for the future roadway widening that is under design by Tulsa County. The design of the waterline was completed in 2022 but requires some modifications due to changes in the Tulsa County Roadway projects in this area. Tulsa County’s roadway project is divided into two separate projects. The first is from Elm Place to 9th Street and the second is from 9th Street to 23rd Street. This amendment is to split the waterline design into two separate projects to reflect the split in the roadway design.
Amendment 2 with Native Strategies, LLC has been negotiated for $8,989.84.
Cost: $8,989.84
Funding Source: OWRB Loan
Requested By: Charlie Bright, P.E., Director of Engineering & Construction
Approved By: City Manager’s Office
Attachments: WL22010 Omaha WL Relocation Amendment No.2_Legal Signed
Recommendation:
recommend
Approve and authorize execution of Amendment No. 2 to Professional Consulting Agreement with Native Strategies, LLC for the Omaha Waterline Improvements Project (Project No. WL22010).
end