Legislation Details

File #: 26-882    Name:
Type: Consent Item Status: Agenda Ready
File created: 6/8/2026 In control: Broken Arrow Municipal Authority
On agenda: 6/15/2026 Final action:
Title: Ratify the approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements (2454140)
Attachments: 1. Verdigirs River WTP Raw Water Pump - PCO1 36 Inch Mag Meter 5.4
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 06-15-2026

 

Title:

title

Ratify the approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements (2454140)

End

 

Background:

The Verdigris River Water Treatment Plant Raw Water Pump Station Improvements is a project that will add another raw water pump house and upgrade the electrical system.   

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     Replace a 36” flow meter at the raw water project. 

Total time added to contract is:

-                     28 weeks for procurement.

 

 The total cost for Change Order #1 amounts to $77,955.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $77,955.00

Total Cost of Change Orders:                                          $77,955.00

Original Contract Amount:                                          $1,094,400.00

Revised Contract Amount:                                          $1,172,355.00

 

Percent Change in Contract:                                          7.12%

Applicable to Comp. Bid Act:                     7.12%

Cost:                                                                $77,955.00

Funding Source:                     OWRB Loan

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Verdigris River WTP Raw Water Pump - PCO1 36 inch Mag Meter 5.4
 

Recommendation:

recommend

Ratify and approve of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements (2454140)

end