Broken Arrow Municipal Authority
Meeting of: 05-20-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Cook Consulting, LLC and Innovation District Lift Station (S24020)
End
Background:
The Innovation District lift station project is to construct a lift station and install a sewer main that connects the innovation district with the south side of the turn pike.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Provide Control Panel parts in lieu of City Supplied Change Pumps to Flygt. This was requested by the Utility Dept.
- There is no change in contract time.
The total cost for Change Order #1 amounts to $17,826.97
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $17,826.97
Total Cost of Change Orders: $17,826.97
Original Contract Amount: $2,111,729.29
Revised Contract Amount: $2,129,556.26
Percent Change in Contract: 0.84%
Applicable to Comp. Bid Act: 0.84%
Cost: $0
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Cook Consulting Innovation District Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Cook Consulting LLC for the Innovation District Lift Station (S24020)
end