Title: Approval of and authorization to execute a Professional Consulting Agreement with Garver, LLC for the Bass Pro Booster Pump Station Rehabilitation
Attachments: 1. Bass Pro BPS Rehab Project Agreement- Signed by legal
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 12-19-2023

 

Title:

title

Approval of and authorization to execute a Professional Consulting Agreement with Garver, LLC for the Bass Pro Booster Pump Station Rehabilitation

End

 

Background:

This project is for upgrades to the existing Bass Pro Booster Pump Station. This station is an older booster pump station in our system that provides the water to the First Baptist Elevated Storage Tank which feeds the High-Pressure Zone located around Bass Pro. The High-Pressure zone includes hotels, restaurants, a hospital, other businesses, and residents. With this station being older it is in need of new pumps, improved site security, as well as improved access to the site.

An agreement with Garver, LLC has been negotiated for $146,300 to design, provide bidding documents, bidding assistance, and construction phase services for these improvements.

 

Cost:                                                                $146,300.00

Funding Source:                     OWRB Loan

Requested By:                      Kenneth D. Schwab, P.E., Assistant City Manager- Operations

Approved By:                      City Manager’s Office

Attachments:                                          Professional Consulting Agreement

 

Recommendation:

recommend

Approve and authorize execution of a Professional Consulting Agreement with Garver, LLC for the Bass Pro Booster Pump Station Rehabilitation

end