Broken Arrow Municipal Authority
Meeting of: 03-05-2024
Title:
title
Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of January 2024
End
Background:
In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the City’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the January 2024 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on February 15, 2024.
Over the course of the month of January 2024, the total wastewater collected, treated and discharged was 198.421 million gallons (MG). The average daily effluent flow was 5.298 MG.
This report will be updated on a monthly basis. Staff recommends the Authority acknowledge submittal of the Report.
Cost: None
Funding Source: None
Requested By: Rocky Henkel, Interim Utilities Director
Approved By: City Manager’s Office
Attachments: January Discharge Monitoring Report
January Monthly Operational Report
Recommendation:
recommend
Acknowledge submittal of the January 2024 Monthly Discharge Monitoring Report