Acceptance of and authorization to execute the Change Order #4 with Paragon Contractors, LLC for the Jasper St & Aspen Intersection Improvements (ST2031)
End
Background:
The Jasper Street and Aspen Intersection project is to widen the intersection and mill and overlay Aspen from Jasper to Shreveport.
Change Order #4 addresses the following additions/deletions/changes to the contract:
- Waterline Scope not performed (Deduct)
- Excavate Unsuitable Soils
- Traffic Control Adds
- There is a 26 day change in contract time.
The total cost for Change Order #4 amounts to ($98,660.41)
The additional cost associated with these changes is as follows:
Previous Change Orders: $216,775.63
This Change Order(s): ($98,660.41)
Total Cost of Change Orders: $118,115.22
Original Contract Amount: $2,373,118.11
Revised Contract Amount: $2,491,233.33
Percent Change in Contract: 9.67%
Applicable to Comp. Bid Act: 4.98%
Cost: ($98,660.41)
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: CO 04 Jasper and Aspen Intersection
Recommendation:
recommend
Approve and authorize execution of Change Order #4 with Paragon Contractors, LLC for the Jasper and Aspen Intersection Improvements (ST2031)
end