Approval of and authorization to execute an Amendment No. 2 to Professional Services Agreement with Jacobs Engineering Group, Inc. and the Regional Metropolitan Utility Authority (RMUA) for Haikey Creek Wastewater Treatment Plant (WWTP) Biosolids Improvements (BAMA Project No. HC21020, RMUA Project No. RMUA ES 2020-11)
End
Background:
RMUA and BAMA representatives, selected Jacobs Engineering Group, Inc. (Jacobs) in 2022 to update the Hakey Creek Wastewater Treatment Plant (HCWWTP) Biosolids Master Plan and Facility Plan and design the chosen alternative. Amendment No. 2 is for Jacobs to complete a NEPA environmental assessment and cultural survey and to provide design services related to: 1) a new blower building, 2) rehabilitation of the west sludge tank, 3) yard piping from RDTs to holding tanks, 4) removal of old piping and valves for sludge and scum tanks, 5) new office building, and 6) gravity thickener decommissioning.
The Amendment No. 2 with Jacobs Engineering Group, Inc. authorizes additional design services related to the Biosolids Facilities and NEPA environmental assessment/cultural survey. Amendment No. 2 is for $642,068.00 bringing the total Agreement amount to $4,847,882.59, the cost of which will be evenly split between the City of Tulsa and BAMA.
Cost: $321,034.00 (BAMA’s cost)
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Engineering and Construction Director
Approved By: City Manager’s Office
Attachments: Amendment No.2 for Professional Services Agreement
Recommendation:
recommend
Approve and authorize execution of Amendment No. 2 to Professional Services Agreement with Jacobs Engineering Group, Inc. and the Regional Metropolitan Utility Authority (RMUA) for Haikey Creek Wastewater Treatment Plant (WWTP) Biosolids Improvements (BAMA Project no. HC21020, RMUA Project no. RMUA ES 2020-11)