LEGISLATIVE RESEARCH CENTER
File #: 24-1476    Name:
Type: Consent Item Status: Agenda Ready
File created: 10/25/2024 In control: Broken Arrow Municipal Authority
On agenda: 11/5/2024 Final action:
Title: Approval of and authorization to execute an Amendment No. 2 to Professional Services Agreement with Jacobs Engineering Group, Inc. and the Regional Metropolitan Utility Authority (RMUA) for Haikey Creek Wastewater Treatment Plant (WWTP) Biosolids Improvements (BAMA Project No. HC21020, RMUA Project No. RMUA ES 2020-11)
Attachments: 1. RMUA BAMA HCWWTP Biosolids Jacobs Amendment 2
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 11-05-2024

 

Title:

title

Approval of and authorization to execute an Amendment No. 2 to Professional Services Agreement with Jacobs Engineering Group, Inc. and the Regional Metropolitan Utility Authority (RMUA) for Haikey Creek Wastewater Treatment Plant (WWTP) Biosolids Improvements (BAMA Project No. HC21020, RMUA Project No. RMUA ES 2020-11)

End

 

Background:

RMUA and BAMA representatives, selected Jacobs Engineering Group, Inc. (Jacobs) in 2022 to update the Hakey Creek Wastewater Treatment Plant (HCWWTP) Biosolids Master Plan and Facility Plan and design the chosen alternative. Amendment No. 2 is for Jacobs to complete a NEPA environmental assessment and cultural survey and to provide design services related to: 1) a new blower building, 2) rehabilitation of the west sludge tank, 3) yard piping from RDTs to holding tanks, 4) removal of old piping and valves for sludge and scum tanks, 5) new office building, and 6) gravity thickener decommissioning.

The Amendment No. 2 with Jacobs Engineering Group, Inc. authorizes additional design services related to the Biosolids Facilities and NEPA environmental assessment/cultural survey.  Amendment No. 2 is for $642,068.00 bringing the total Agreement amount to $4,847,882.59, the cost of which will be evenly split between the City of Tulsa and BAMA.

 

Cost:                                                                $321,034.00 (BAMA’s cost)

Funding Source:                     OWRB Loan

Requested By:                      Charlie Bright, PE, Engineering and Construction Director

Approved By:                      City Manager’s Office

Attachments:                                          Amendment No.2 for Professional Services Agreement

Recommendation:

recommend

Approve and authorize execution of Amendment No. 2 to Professional Services Agreement with Jacobs Engineering Group, Inc. and the Regional Metropolitan Utility Authority (RMUA) for Haikey Creek Wastewater Treatment Plant (WWTP) Biosolids Improvements (BAMA Project no. HC21020, RMUA Project no. RMUA ES 2020-11)