LEGISLATIVE RESEARCH CENTER
File #: 18-400    Name:
Type: Consent Item Status: Passed
File created: 3/26/2018 In control: Broken Arrow City Council
On agenda: 4/3/2018 Final action: 4/3/2018
Title: Award of the lowest responsible bid to H&G Paving Contractors, approve and authorize execution of a construction contract for Cold Milling Streets
Attachments: 1. Certified Bid Tabulation

Broken Arrow City Council

                                                                                               Meeting of: 04-03-18

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Award of the lowest responsible bid to H&G Paving Contractors, approve and authorize execution of a construction contract for Cold Milling Streets

End

Background:

To assist the Streets and Stormwater Department in their street maintenance program, the Engineering and Construction Department advertised a “non-encumbered” contract for Milling Asphalt Streets.  The contract will be awarded based on unit prices, then work orders will be issued against the main contract for various milling jobs.  The contract will be awarded for a one-year period, with up to two possible renewals at the same unit prices.

 

The project was advertised for bids on February 19 and February 26, 2018.  Bids were opened on March 20, 2018 and four (4) bids were received.  The Certified Bid Tabulation is attached.  The lowest responsible bidder was H&G Paving Contractors, with a bid of $205,500.00.

 

Staff recommends awarding the bid in the amount of $205,500.00 to H&G Paving Contractors.

 

Funding for individual work orders will come from various sources, including the Street Sales

Tax Fund, General Obligation Bonds Funds and Sales Tax Capital Improvement Fund.

 

Cost:                                                                $205,500.00

Prepared By:                                           Alex M. Mills, P.E., Director of Engineering and Construction

Reviewed By:                                          Streets & Stormwater Department
                                    Finance Department

                                    Legal Department
                                    Assistant City Manager - Operations

Approved By:                      Michael L. Spurgeon, City Manager                                   

Attachments:                                          Certified Bid Tabulation

Recommendation:

Award the lowest responsible base bid to H&G Paving Contractors, and approve and authorize execution of a construction contract for Cold Milling Streets.