Legislation Details

File #: 26-1639    Name:
Type: Consent Item Status: Agenda Ready
File created: 10/8/2026 In control: Broken Arrow City Council
On agenda: 10/20/2026 Final action:
Title: Approval of and authorization to execute Change Order #4 with Tri-Star Construction, LLC for the Houston Street Improvements – 23rd to Old Highway 51 (ST1926A and WL26040)
Attachments: 1. Houston ST 1926A Change Order 4
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 10-20-2026

 

Title:

title

Approval of and authorization to execute Change Order #4 with Tri-Star Construction, LLC for the Houston Street Improvements - 23rd to Old Highway 51 (ST1926A and WL26040)

End

 

Background:

 The Houston St Improvements project will be to rehabilitate the water line from 23rd st to Old Highway 51. The project will also widen the road to allow for more traffic. 

Change Order #4 addresses the following additions/deletions/changes to the contract:

-                     Provide an additional traffic control sequence, Phase IV, for the purpose of following ODOT recommendations regarding pavement installation phasing and flex tabs

 

 The total cost for Change Order #4 amounts to $13,875.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $77,185.38

This Change Order(s):                                                               $13,875.00

Total Cost of Change Orders:                                          $91,060.38

Original Contract Amount:                                          $4,015000.00

Revised Contract Amount:                                          $4,106,060.38

 

Percent Change in Contract:                                          2.27%

Applicable to Comp. Bid Act:                     1.10%

Cost:                                                                $13,875.00

Funding Source:                     2018 GO BOND

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Houston St 1926A Change Order 4

Recommendation:

recommend

Approve and authorize the execution of Change Order #4 with Tri-Star Construction, LLC for the Houston Street Improvements - 23rd to Old Highway 51 (ST1926A and WL26040)

 

end