Broken Arrow Municipal Authority
Meeting of: 05-20-2025
Title:
title
Approval of and authorization to execute a Construction Contract with the Regional Metropolitan Utility Authority (RMUA) and Crossland Heavy Contractors, Inc. for the Construction of the fiscal year 2025 Capital Equipment Replacement Projects
End
Background:
The Capital Equipment Replacement Project is for the annual replacement of equipment at the Regional Metropolitan Utility Authority (RMUA) Haikey Creek Wastewater Treatment Plant (HCWWTP). This project is to replace capital equipment identified in the strategic asset management plan. Equipment to be replaced includes: lighting upgrades, Operations and Laboratory Upgrades, Grit Basin Deflector improvements, Maintenance Building, and Haikey Creek Lift Station Conveyor Screen Equipment Trough Liner Replacement.
The Construction fee for this project is $486,000.00 of which BAMA and TMUA each pay 50% ($243,000.00). Funding for the improvements will be from the Utilities Department Operations and Maintenance (O&M) budget.
Cost: $243,000.00
Funding Source: Utilities O&M Budget
Requested By: Charlie Brights, P.E., Director of Engineering & Construction
Approved By: City Manager’s Office
Attachments: RMUA Construction Contract
Recommendation:
recommend
Approve and authorize execution of Construction Contract with the Regional Metropolitan Utility Authority (RMUA) and Crossland Heavy Contractors, Inc. for the Construction of the fiscal year 2025 Capital Equipment Replacement Projects
end