Title: Approval of and authorization to execute the Change Order No. 1 with Paragon Contractors, LLC for the Jasper Street & Aspen Intersection Improvements (ST2031)
Attachments: 1. CO_01_Shreveport_Intersection_Modifications_Paragon_CO_1-5_combined
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 12-02-2025

 

Title:

title

Approval of and authorization to execute the Change Order No. 1 with Paragon Contractors, LLC for the Jasper Street & Aspen Intersection Improvements (ST2031)

End

 

Background:

 The Jasper Street and Aspen Intersection project is to widen the intersection and mill and overlay Aspen from Jasper to Shreveport.

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     Shreveport Intersection Concrete Curb Island High Early Concrete

-                     Portable Changeable Message Signs for Road Closure

-                     Traffic Control for Detour

-                     Concrete Flume

-                     Traffic control removal and temp flex tabs.

 

-                     There is a 1 day change in contract time.

 

 The total cost for Change Order #1 amounts to $13,568.27

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0.00

This Change Order(s):                                                               $13,568.27

Total Cost of Change Orders:                                          $13,568.27

Original Contract Amount:                                          $2,373,118.11

Revised Contract Amount:                                          $2,386,686.38

 

Percent Change in Contract:                                          0.57%

Applicable to Comp. Bid Act:                     0.57%

Cost:                                                                $13,568.27

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          CO 01 Shreveport intersection modifications
 

Recommendation:

recommend

Approve and authorize execution of Change Order #1 with Paragon Contractors, LLC for the Jasper and Aspen Intersection Improvements (ST2031)