Approval of and authorization to execute the Change Order No. 1 with Paragon Contractors, LLC for the Jasper Street & Aspen Intersection Improvements (ST2031)
End
Background:
The Jasper Street and Aspen Intersection project is to widen the intersection and mill and overlay Aspen from Jasper to Shreveport.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Shreveport Intersection Concrete Curb Island High Early Concrete
- Portable Changeable Message Signs for Road Closure
- Traffic Control for Detour
- Concrete Flume
- Traffic control removal and temp flex tabs.
- There is a 1 day change in contract time.
The total cost for Change Order #1 amounts to $13,568.27
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $13,568.27
Total Cost of Change Orders: $13,568.27
Original Contract Amount: $2,373,118.11
Revised Contract Amount: $2,386,686.38
Percent Change in Contract: 0.57%
Applicable to Comp. Bid Act: 0.57%
Cost: $13,568.27
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: CO 01 Shreveport intersection modifications
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Paragon Contractors, LLC for the Jasper and Aspen Intersection Improvements (ST2031)
end