LEGISLATIVE RESEARCH CENTER
File #: 25-419    Name:
Type: Consent Item Status: Agenda Ready
File created: 3/24/2025 In control: Broken Arrow Municipal Authority
On agenda: 4/1/2025 Final action:
Title: Ratify the acceptance of and authorization to accept the Change Order No. 1 for the Tiger Hill water tank from Kimery Painting Inc for the center pole replacement and floor testing (Project No. 2454460)
Attachments: 1. Tiger_Hill_Tank_Change_Order_1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow Municipal Authority
Meeting of: 4-1-2025

Title:
title
Ratify the acceptance of and authorization to accept the Change Order No. 1 for the Tiger Hill water tank from Kimery Painting Inc for the center pole replacement and floor testing (Project No. 2454460)
End
Background:
On March 18, 2025, COBA approved the Change Order 1 for the Tiger Hill water tank project.
The Tiger Hill east water tank restoration project is to restore a 2 million gallon water tank. The tank was in disrepair and needed to be fixed and repainted. When the tank was emptied, it was found that the floor was in worse shape than anticipated. The floor welds need to be tested for strength and leaks. The center column was found to be in worse shape than originally thought as well. This needs to be repaired to ensure the integrity of the tank.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Cost associated with the testing and coating of floor weld seams
- Engineering Cost
- Additional Tank Bracing
- Deduction for not coating tank floor
- Twenty-one Days for column repairs and weld tasting.
The total cost for Change Order #1 amounts to $53,200.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $53,200.00
Total Cost of Change Orders: $53,200.00
Original Contract Amount: $1,042,600.00
Revised Contract Amount: $1,095,800.00
Percent Change in Contract: 5.10%
Applicable to Comp. Bid Act: 2.80%

Cost: $1,095,800.00
Funding Source: OWRB Loan

Requested By: Charlie Bright, P.E., Engineering and Construction Director

Approved By: City Manager's Office
Attachments: Change Order 1 Tiger Hill East Tank Restoration
Recommendation:
recommend
Accept the Change Order #1 for the Tiger Hill water tank from Kimery Painting Inc for the center pole replacement and flo...

Click here for full text