Approval of and authorization to execute the Service Agreement with Regional Metropolitan Utility Authority (RMUA) for the Haikey Creek Wastewater Treatment Facility
End
Background:
Since 1974, Broken Arrow and Tulsa have shared responsibility for the operation and maintenance of the Haikey Creek Wastewater Treatment Facilities. The proposed five-year service contract between the Broken Arrow Municipal Authority (BAMA) and the Regional Metropolitan Utility Authority (RMUA) will continue this longstanding partnership and establish the terms for continued wastewater treatment services.
The contract outlines the parties’ responsibilities for the operation and maintenance of the facilities and the provision of related services. Approval will support the continued treatment of wastewater conveyed from Broken Arrow to the Haikey Creek facilities.
Although the contract is between BAMA and RMUA, the City of Broken Arrow provides wastewater pretreatment services to RMUA under the agreement. Therefore, staff requests that the City Council authorize BAMA to enter into the proposed five-year service contract with RMUA.
Cost: N/A
Funding Source: N/A
Requested By: Timothy S. Robins, P.E., C.F.M., Utilities Director
Approved By: City Manager’s Office
Attachments: Haikey Creek WWTP RMUA Service Agreement
Recommendation:
recommend
Approve and execute the Service Agreement with RMUA for the Haikey Creek Wastewater Treatment Facility