File created: 12/12/2016 In control: Broken Arrow City Council
On agenda: 12/20/2016 Final action:
Title: Approval of and authorization to execute an Agreement for Professional Consultant Services with CEC Corporation for the Design of Olive Avenue Improvements from Kenosha Street to Albany Street (Project Number ST1710)
Attachments: 1. Agreement executed by the Asst City Attorney

Broken Arrow City Council

                                                                                               Meeting of:  12-20-2016

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Approval of and authorization to execute an Agreement for Professional Consultant Services with CEC Corporation for the Design of Olive Avenue Improvements from Kenosha Street to Albany Street (Project Number ST1710)

End

Background:

The Olive Avenue (South 129th East Avenue) Improvements from Kenosha Street (East 71st Street South) to Albany Street (East 61st Street South) is a 2014 Streets GO Bond project.  The Bond issue calls for widening Olive Avenue from Kenosha Street to Albany Street including required appurtenances and acquisition of required easements and right-of-way.  Letters of Interest and Statements of Qualifications were received for this project and CEC Corporation was chosen by a selection committee consisting of Streets and Stormwater and Engineering and Construction Departments.

The Engineering and Construction Department prepared the attached agreement with CEC Corporation in the amount of $348,450.00.  Funding for the design and construction work will be from the 2014 Streets General Obligation Bond.

 

Cost:                                                                $348,450.00

Prepared By:                                           Alex M. Mills, P.E., CFM, Director of Engineering and Construction

Reviewed By:                                          Streets and Stormwater Department
                                    Finance Department
                                    Assistant City Manager - Operations
                                    Legal Department

Approved By:                      Michael L. Spurgeon, City Manager
                                   

Attachments:                                          Agreement for Professional Consultant Services for the Design of Olive Avenue Improvements from Kenosha Street to Albany Street
                                   

Recommendation:

Approve the Agreement for Professional Consultant Services with CEC Corporation and authorize its execution.