Approval of and authorization to execute Change Order #2 with Tri-Star Construction, LLC for the Houston Street Improvements - 23rd to Old Highway 51 (ST1926A and WL26040)
End
Background:
The Houston St Improvements project will be to rehabilitate the water line from 23rd st to Old Highway 51. The project will also widen the road to allow for more traffic.
Change Order #2 addresses the following additions/deletions/changes to the contract:
- Adjust bid quantities to what was required to complete the waterline portion of the project.
The total cost for Change Order #2 amounts to $29,262.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $30,997.82
This Change Order(s): $29,262.00
Total Cost of Change Orders: $60,259.82
Original Contract Amount: $4,015000.00
Revised Contract Amount: $4,075,259.82
Percent Change in Contract: 1.50%
Applicable to Comp. Bid Act: 0.50%
Cost: $29,262.00
Funding Source: 2018 GO BOND
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: 22601969-ST1926A_Houston St Improv’ts CO 02
Recommendation:
recommend
Approve and authorize the execution of Change Order #2 with Tri-Star Construction, LLC for the Houston Street Improvements - 23rd to Old Highway 51 (ST1926A and WL26040)