File #: 25-773    Name:
Type: Presentations Status: Agenda Ready
File created: 5/28/2025 In control: Broken Arrow City Council
On agenda: 6/2/2025 Final action:
Title: Presentation regarding requested lane closure at the intersection of South Elm Place and West Houston Street by AWP Safety
Attachments: 1. Complete_with_Docusign_Lane_Closures_S_Elm_P
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 06-02-2025

 

Title:

title

Presentation regarding requested lane closure at the intersection of South Elm Place and West Houston Street by AWP Safety

End

 

Background:

The purpose of this item is to provide notification of an upcoming lane closure which is required to ascertain the depth of some existing Windstream installation which runs under the roadway. Telecom provider is trying to confirm if there will be conflicts with a future sanitary sewer improvement being designed by HUB Engineering. The associated public project is titled South Park South Relief Line and Houston Street Trenchless Sanitary Sewer Rehabilitation. The associated project number is 2154280.

 

The closure is expected to take place June 10th, 2025. It will last from 7am to roughly 3pm. The approved lane closure has been attached for additional details related to traffic control setup.

 

Cost:                                                                $0

Funding Source:                     None

Requested By:                      Charlie Bright, P.E. , Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Complete_with_Docusign_Lane_Closures_S_Elm_P

 

Recommendation:

recommend

Information only