File #: 23-1126    Name:
Type: Consent Item Status: Agenda Ready
File created: 8/25/2023 In control: Broken Arrow Municipal Authority
On agenda: 9/5/2023 Final action:
Title: Acknowledgement of submittal of the Broken Arrow Municipal Authority's Wastewater Discharge Monitoring Report for the month of July 2023
Attachments: 1. July Discharge Monitoring Report, 2. July Monthly Operational Report
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 09-05-2023

 

Title:

title

Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of July 2023

End

 

Background:

In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the City’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the July 2023 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on August 15, 2023.

Over the course of the month of July 2023, the total wastewater collected, treated and discharged was 165.927 million gallons (MG).  The average daily effluent flow was 5.094 MG.

This report will be updated on a monthly basis.  Staff recommends the Authority acknowledge submittal of the Report.

 

Cost:                                                                None

Funding Source:                     None

Requested By:                      Charles Vokes, Utilities Director

Approved By:                      City Manager’s Office

Attachments:                                          July Discharge Monitoring Report
                                    July Monthly Operational Report

 

Recommendation:

recommend

Acknowledge submittal of the July 2023 Monthly Discharge Monitoring Report