File #: 25-768    Name:
Type: Consent Item Status: Agenda Ready
File created: 5/27/2025 In control: Broken Arrow Municipal Authority
On agenda: 6/2/2025 Final action:
Title: Approval of and authorization to execute Change Order No. 4 with Crossland Heavy Construction for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)
Attachments: 1. Change_Order_4_LLWWTP_Disinfection
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of:  06-02-2025

 

Title:

title

Approval of and authorization to execute Change Order No. 4 with Crossland Heavy Construction for the Lynn Lane Waste Water Treatment Plant  Disinfection Improvements (S1905)

End

 

Background:

 The LLWWTP Disinfection system improvements project is nearly complete and needs the following Change order to achieve substantial completion.

Change Order #4 addresses the following additions/deletions/changes to the contract:

-                     To cover the overrun of asphalt to cover the contract price

 

-                     0 days in added time.

 

 The total cost for Change Order #4 amounts to $51,400.21

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $40,262.05

This Change Order(s):                                                               $11,312.00

Total Cost of Change Orders:                                          $51,574.05

Original Contract Amount:                                          $5,841,000.00

Revised Contract Amount:                                          $5,892,674.05

 

Percent Change in Contract:                                          0.88%

Applicable to Comp. Bid Act:                     0.88%

Cost:                                                                $5,892,674.05

Funding Source:                     OWRB Loan

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          LLWWTP Disinfection CO 4 

Recommendation:

recommend

Approve and authorize execution of Change Order #4 with Crossland Heavy Contractors for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)

end