Broken Arrow Municipal Authority
Meeting of: 4-15-2025
Title:
title
Ratification of Change Order No. 3 for the Lynn Lane Wastewater Treatment Plant Disinfection Improvements with Crossland Heavy Contractors (Project No. S1905)
End
Background:
The LLWWTP Disinfection system improvements project is nearly complete and needs the following Change order to properly get the system working for that we can achieve substantial completion.
Change Order #3 addresses the following additions/deletions/changes to the contract:
- Purchase and installation of a new Actuator
- 14 days in added time.
The total cost for Change Order #3 amounts to $51,400.21
The additional cost associated with these changes is as follows:
Previous Change Orders: ($11,138.16)
This Change Order(s): $51,400.21
Total Cost of Change Orders: $40,262.05
Original Contract Amount: $5,841,000.00
Revised Contract Amount: $5,881,262.05
Percent Change in Contract: 0.68%
Applicable to Comp. Bid Act: 0.88%
Cost: $5,881,262.05
Funding Source: OWRB Loan
Requested By: Charlie Bright, P.E., Engineering and Construction Director
Approved By: City Manager’s Office
Attachments: Emergency by-pass system CO 3
Recommendation:
recommend
Ratify Change Order No. 3 for the Lynn Lane Wastewater Treatment Plant Disinfection Improvements with Crossland Heavy Contractors (Project No. S1905)
end