Review of bids received, award of the lowest responsible bid to Brashear Pavement Coatings, LLC, and approval of and authorization to execute a construction contract for Crack Fill, Sealcoat, and Restripe of Nienhuis Park Football Complex Parking Lot (Project No. 156004)
End
Background:
Project 156004 is funded through the Sales Tax Capital Improvement Fund in the amount of $45,000.00. The work consists of crack fill, sealcoat and restriping of the existing parking lot located near the Nienhuis Park Football Complex.
Bids were advertised on February 26 and March 4, 2016, and bids were opened on March 23, 2016. Nine (9) companies were contacted for bids. Six (6) companies submitted bids. The lowest responsible bidder with options was Brashear Pavement Coatings, LLC, in the amount of $35,900.00. Staff recommends that the bid be awarded to Brashear
Cost: $35,900.00
Prepared By: Scott Esmond, Director of Parks and Recreation
Reviewed By: Parks and Recreation Department
Finance Department
Assistant City Manager - Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: RFP 16.138
Recommendation: Award of the lowest responsible bid to Brashear Pavement Coatings, LLC, and approve and authorize execution of a construction contract for Crack fill, Sealcoat, and Restripe of Nienhuis Park Football Complex Parking Lot (Project No. 156004).