Title: Review of bids received, award of the lowest responsible bid to Brashear Pavement Coatings, LLC, and approval of and authorization to execute a construction contract for Crack Fill, Sealcoat, and Restripe of Nienhuis Park Football Complex Parking Lot (Project No. 156004)
Attachments: 1. RFP 16.138 Nienhuis complex bid tab

Broken Arrow City Council

Meeting of: 04-19-16

 

To:                     Mayor and City Council

From:                     Office of the Parks and Recreation Department

Title:

title

                     Review of bids received, award of the lowest responsible bid to Brashear Pavement Coatings, LLC, and approval of and authorization to execute a construction contract for Crack Fill, Sealcoat, and Restripe of Nienhuis Park Football Complex Parking Lot (Project No. 156004)

End

Background:

Project 156004 is funded through the Sales Tax Capital Improvement Fund in the amount of $45,000.00.  The work consists of crack fill, sealcoat and restriping of the existing parking lot located near the Nienhuis Park Football Complex. 

Bids were advertised on February 26 and March 4, 2016, and bids were opened on March 23, 2016.  Nine (9) companies were contacted for bids.  Six (6) companies submitted bids.  The lowest responsible bidder with options was Brashear Pavement Coatings, LLC, in the amount of $35,900.00.  Staff recommends that the bid be awarded to Brashear

Cost:                                                                $35,900.00

Prepared By:                                           Scott Esmond, Director of Parks and Recreation

Reviewed By:                                          Parks and Recreation Department
                                    Finance Department
                                    Assistant City Manager - Operations

                                    Legal Department

Approved By:                      Michael L. Spurgeon, City Manager

Attachments:                                          RFP 16.138

Recommendation:                     Award of the lowest responsible bid to Brashear Pavement Coatings, LLC, and approve and authorize execution of a construction contract for Crack fill, Sealcoat, and Restripe of Nienhuis Park Football Complex Parking Lot (Project No. 156004).

 

SJE/ph