Title: Acceptance of and authorization to execute the Change Order #3 with Paragon Contractors, LLC for the Jasper St & Aspen Intersection Improvements (ST2031)
Attachments: 1. CO03_Waterline_Shoring
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 05-05-2026

 

Title:

title

Acceptance of and authorization to execute the Change Order #3 with Paragon Contractors, LLC for the Jasper St & Aspen Intersection Improvements (ST2031)

End

 

Background:

 The Jasper Street and Aspen Intersection project is to widen the intersection and mill and overlay Aspen from Jasper to Shreveport.

Change Order #3 addresses the following additions/deletions/changes to the contract:

-                     Shoring for Installation of 60” HDPE at Creek Due to Unsuitable Soil

-                     Waterline

-                     Restock Casing Fee

-                     Remove Lime and Lime Stabilized subgrade

-                     There is a 20 day change in contract time.

 

 The total cost for Change Order #3 amounts to $189,921.01

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $26,854.62

This Change Order(s):                                                               $189,921.01

Total Cost of Change Orders:                                          $216,775.63

Original Contract Amount:                                          $2,373,118.11

Revised Contract Amount:                                          $2,708,417.65

 

Percent Change in Contract:                                          14.13%

Applicable to Comp. Bid Act:                     9.13%

Cost:                                                                $189,921.01

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          CO 03 Shreveport intersection modifications
 

Recommendation:

recommend

Approve and authorize execution of Change Order #3 with Paragon Contractors, LLC for the Jasper and Aspen Intersection Improvements (ST2031)