Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 25-677    Name:
Type: Consent Item Status: Agenda Ready
File created: 5/8/2025 In control: Broken Arrow City Council
On agenda: 5/20/2025 Final action:
Title: Acceptance of the Drainage Advisory Committee's recommendation to City Council to expend funds to construct erosion control measures in the Bristol Ponds south detention pond and in the channel between Bristol Ponds and Elm Place
Attachments: 1. Bristol Ponds Packet Case 25-006
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 05-20-2025

 

Title:

title

Acceptance of the Drainage Advisory Committee’s recommendation to City Council to expend funds to construct erosion control measures in the Bristol Ponds south detention pond and in the channel between Bristol Ponds and Elm Place

End

 

Background:

The case was brought before the Drainage Advisory Committee on April 28, 2025 for construction funds. The Committee voted 7-0 to recommend approval of expenditure of funds.

The proposed project is near the Bristol Ponds subdivision located west of Elm Place and north of Washington St.

Staff investigated the site and found that the channel on both public and private does not appear to have been constructed per plan.  It appears that erosive velocities were not mitigated.  Erosion is present along the channel and the pond bank.

Bristol Ponds is a private subdivision platted in 2005. The City owns the channel between Bristol Ponds and Elm Place. The City also owns land south of the pond. The pond and its’ bank is privately owned.

Construction is anticipated to occur in the Summer of 2025.

Staff is requesting $230,000.00 of the 2018 GO Bond, Proposition 6 for construction costs.

This area flows to Haikey Creek.

 

Cost:                                                                $230,000.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Drainage Report, Exhibits   

 

Recommendation:

recommend

Accept the Drainage Advisory Committee’s recommendation to approve expenditure of funds to construct erosion control measures in the Bristol Ponds south detention pond and in the channel between Bristol Ponds and Elm Place.

end