Approval of and authorization to execute Change Order #1 with Wyatt Contracting. Inc (SW1910)
End
Background:
The Stoneridge and Elm Drainage Improvements project completed a detention pond with an outlet structure.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Delete 196 LF of Temporary Silt Fence, delete 2 sediment filters, delete 720 LF of ditch liner protection, delete 1 stabilized construction entrance, delete 119 CY of 10’ wide gravel access road, delete 1 low water crossing, and delete 3 rock check dams.
Total time added to contract is:
- Time was added in a work change directive due to sodding.
The total cost for Change Order #1 amounts to ($31,416.80)
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): ($31,416.80)
Total Cost of Change Orders: ($31,416.80)
Original Contract Amount: $375,449.50
Revised Contract Amount: $344,03.70
Percent Change in Contract: -8.37%
Applicable to Comp. Bid Act: 0%
Cost: ($31,416.80)
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Stoneridge Towne Center Change Order 1
Recommendation: