Legislation Details

File #: 26-1337    Name:
Type: Consent Item Status: Agenda Ready
File created: 8/19/2026 In control: Broken Arrow City Council
On agenda: 9/1/2026 Final action:
Title: Approval of and authorization to execute a Professional Consultant Agreement with Selser Shaefer Architects for the Construction Design to replace the Roof on the Public Safety Complex Annex Building (aka the EMS Building) (Project No. 191711)
Attachments: 1. EMS Roof Replacement.Legal Signed - 191711
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 09-01-2026

 

Title:

title

Approval of and authorization to execute a Professional Consultant Agreement with Selser Shaefer Architects for the Construction Design to replace the Roof on the Public Safety Complex Annex Building (aka the EMS Building) (Project No. 191711)

End

 

Background:

This project is to replace the roof on the Annex Building in Public Safety Complex that houses the EMS department. This roof has reached the end of its service life and needs to be replaced.

An agreement has been negotiated with Selser Shaefer Architects (aka Narrate) to investigate the existing roof conditions, make recommendations on a new roofing system, and then prepare construction documents for the roof replacement. The agreement is for $ 14,100.00

 

Cost:                                                                $ 14,100.00

Funding Source:                     STCI

Requested By:                      Charlie Bright, P.E, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          EMS Roof Replacement.Legal Signed - 191711

 

Recommendation:

recommend

Approve of and authorize to execute a Professional Consultant Agreement with Selser Shaefer Architects for the Construction Design to replace the Roof on the Public Safety Complex Annex Building (aka the EMS Building) (Project No. 191711)