LEGISLATIVE RESEARCH CENTER
File #: 25-453    Name:
Type: General Business Status: Agenda Ready
File created: 3/26/2025 In control: Broken Arrow Economic Development Authority
On agenda: 4/1/2025 Final action:
Title: Presentation, discussion and possible direction by the Authority regarding an Economic Development Agreement by and among Oaktrust Development, Broken Arrow Economic Development Authority and City of Broken Arrow
Sponsors: Broken Arrow City Council
Broken Arrow Economic Development Authority
Meeting of: 04/01/2025



Title:
title
Presentation, discussion and possible direction by the Authority regarding an Economic Development Agreement by and among Oaktrust Development, Broken Arrow Economic Development Authority and City of Broken Arrow
End

Background:
On June 29, 2021, BAEDA and the City of Broken Arrow entered into an Economic Development Agreement with OakTrust Development, LLC to promote economic development within a Tax Increment District along the east side of South Aspen Avenue. The agreement outlined specific development commitments, including:
* Construction of a 60,000 square-foot Reasor's Grocery Store by June 30, 2023
* Development of a 168-unit multi-family apartment complex by June 30, 2023.
* Development of over 200,000 square feet of new retail and commercial space by June 30, 2024.
* Construction of Project Site improvements, including a traffic signal at Norfolk, with a financial commitment from the Authority up to $5,530,000.00.
Subsequent amendments to the Agreement were approved to address infrastructure changes and delays encountered by the Developer. The Fourth Amendment, approved most recently, adjusted the timeline as follows:
* Reasor's Grocery Store completion extended to November 1, 2024.
* Multi-family apartment complex construction start extended to no later than March 31, 2025 with completion extended to September 30, 2026.
* 200,000 square feet of commercial and retail space construction start date extended to September 30, 2024 with a completion extended to December 31, 2025.
Obligations and Current Status:
1. 168-Unit Multi-Family Apartment Complex
o Obligation: Developer agrees to develop, construct or cause to be constructed within the Project Site a 168-unit multi-family apartment complex beginning no later than March 31, 2025 and shall be completed no later than September 30, 2026;
o Status: Construction has not yet begun.
2. 200,000 Square Feet of Commercial a...

Click here for full text