Broken Arrow City Council
Meeting of: 04-07-2026
Title:
title
Approval of and authorization to execute Change Order No. 1 with Grade Line Construction, LLC for the Wedgewood Residential Streets Concrete Panel Replacement project (ST22100)
End
Background:
The Wedgewood Residential Streets Concrete Panel Replacement project is to replace some of the roads in the Wedgewood neighborhood. The project did not have some roads in the contract and therefore this change order is needed to get most of the roads completed.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- At the directions of the COBA Contract Administrator, added approximately 822 LF of full width road reconstruction on W Knoxville street and S Oak Avenue
- At the direction of the COBA Contract Administrator, added 9 inlet replacements on W Knoxville Street and S Oak Avenue
- There is a 45-day change in contract time.
The total cost for Change Order #4 amounts to $326,499.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $326,499.00
Total Cost of Change Orders: $326,499.00
Original Contract Amount: $739,127.40
Revised Contract Amount: $1,065,626.40
Percent Change in Contract: 44.17%
Applicable to Comp. Bid Act: 0.0%
Cost: $326,499.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Wedgewood ST22100-Change Order No. 1
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Grade Line Construction LLC for the Wedgewood Residential Streets Concrete Panel Replacement project (ST22100)
end