Approval of and authorization of Final Acceptance for the public improvements at Elysian Fields located at 121st Street and South Garnett Road
End
Background:
Ira M. Green Construction has completed the construction for Elysian Fields project. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvements are for the paving, sanitary sewer, storm, water, and lift station installations.
The owner desires to donate the public improvements identified above to the City of Broken Arrow. These improvements have an approximate value of $1,654,082.70
Cost: None
Funding Source: N/A
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: COBA Infrastructure Inventory - Elysian Fields
Recommendation:
recommend
Approve and authorize final acceptance and donation of the public improvements at Elysian Fields located at 121st Street and South Garnett Road.