From: Department of Engineering and Construction
Title:
title
Approval of and authorization to execute Change Order C02 for Construction Contract Number 161708, Farmers Market Interactive Water Feature
End
Background:
The Rose District Farmers Market Water Feature is an approximately 1200-square-foot recirculating water feature located along the east boundary of the Farmers Market in the Rose District, 418 South Main Street. The finished surface of the water feature will be granite pavers supported by a pedestal system over a concrete basin. Site work consists of concrete and brick paving, masonry walls, lighting, and relocation of utilities. The construction contract was advertised for bids on February 23 and bids were opened on March 24, 2016. Two (2) bids were received. The awarded low bid was submitted by Magnum Construction, Inc., in the amount of $1,322,541.00, including the allowances for the three procurement contracts.

This Change Order #2 addresses the following additions to the contract:

1. Total Number of Days Added by this Change Order:
- Proposal Request #4: No days Added
- Proposal Request #5: 10 days added due to RFI #7 resolution timeline, direct critical
path effect.
2. Proposal Request # 4: Install electrical brass water stop fitting risers for slab penetrations due to error in procurement package acquisition. Additional water stop fittings per EOR.
3. Proposal Request #5: Add seventeen (17) additional brass water stop fitting risers and conduit raceways for slab penetrations. Change in additional fittings and conduit due to revisions in the lighting controls as corresponded to RFI#7.

Additions to the original contract:
Item #
Item
Unit
Price
Quantity
Amount
CO1-1
PR#4 - Electrical Penetration Water Stops
LS
$7,043.00
1.00
$7,043.00
CO1-2
PR#5 - RFI ...