Background:
The Houston Street Widening from Garnett Road to Olive Avenue project widens that mile from a three lane to a five lane road. This project has dealt with record weather and utility delays.
Change Order #5 addresses the following additions/deletions/changes to the contract:
- This is a reconciliation change order for items that overran and underrun.
- There is a 17 day change in contract time. This time was the time to finish the punch and redo some work on the south lane that needed addressed.
The total cost for Change Order #5 amounts to $150,033.25
The additional cost associated with these changes is as follows:
Previous Change Orders: $100,971.60
This Change Order(s): $150,033.25
Total Cost of Change Orders: $251,004.85
Original Contract Amount: $5,718,000.00
Revised Contract Amount: $5,969,004.85
Percent Change in Contract: 4.39%
Applicable to Comp. Bid Act: 2.17%
Cost: $150,033.25
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Change Order #5 Final Quantity Change Order v2
Recommendation:
recommend
Approve and authorize execution of Change Order #5 with Becco Contractors, Inc. for the Houston Street Widening, Garnett Road to Olive Ave (ST2028).
end