Title: Approval of and authorization to execute a Agreement for Professional Consultant Services with RJN Group, Inc., for Design of Haikey Creek Interceptor Phase 1 Improvements (Project No. S.1605)
Attachments: 1. 160503 RJN Agreement Haikey Creek Sewer Rehab
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow Municipal Authority
Meeting of: 05-03-2016

To: Chairman and Authority Members
From: Department of Engineering and Construction
Title:
title
Approval of and authorization to execute a Agreement for Professional Consultant Services with RJN Group, Inc., for Design of Haikey Creek Interceptor Phase 1 Improvements (Project No. S.1605)
End
Background:
The attached Agreement for Professional Consultant Services with RJN Group, Inc., is for engineering design of 4,570 linear feet of 48-inch slip-lining of an existing 54-inch diameter concrete sanitary sewer interceptor in the Haikey Creek drainage area above the Haikey Creek Lift Station. Also included is rehabilitation of 10 manholes and coordination of closed-circuit television (CCTV) and heavy cleaning of the line to remove excessive solids prior to slip-lining. The Consultant will also provide hydraulic calculations to confirm that the final project will deliver 29.1 million gallons per day (MGD) of peak hydraulic capacity for future ultimate build-out within the basin.

The negotiated amount of the RJN Group agreement for design of the Haikey Creek Interceptor Phase I is $295,505.00. Funding for Engineering will be from the Oklahoma Water Resources Board (OWRB) Financial Assistance Program (FAP) Loan No. 16-0001-L. Staff recommends that the Authority approve the Agreement and authorize its execution.

Cost: $295,505.00
Prepared By: Jeff Bigby, Acting Director of Engineering and Construction
Reviewed By: Utilities Department
Finance Department
Assistant City Manager - Operations
Legal Department


Approved By: Michael L. Spurgeon, City Manager

Attachments: Agreement for Professional Consultant Services



Recommendation:
Approve the Agreement for Professional Consultant Services with RJN Group, Inc., for design of Haikey Creek Interceptor Phase 1 Improvements...

Click here for full text