File #: 25-1636    Name:
Type: General Business Status: Agenda Ready
File created: 11/14/2025 In control: Broken Arrow Municipal Authority
On agenda: 12/2/2025 Final action:
Title: Consideration, discussion, and possible approval of the lowest responsible bid to Crossland Heavy Contractor's, Inc. and authorize execution of a construction contract for the Verdigris River Water Treatment Plant On-Site Hypochlorite Generation System Brine Tank (Project No. 2154350)
Attachments: 1. 20251114-Certified Bid Tabulation-VRWTP Brine Tank.Signed-2154350

Broken Arrow Municipal Authority

Meeting of: 12-2-2025

 

Title:

title

Consideration, discussion, and possible approval of the lowest responsible bid to Crossland Heavy Contractor’s, Inc. and authorize execution of a construction contract for the Verdigris River Water Treatment Plant On-Site Hypochlorite Generation System Brine Tank (Project No. 2154350)

End

 

Background:

The Verdigris River Water Treatment Plant currently has one Brine Tank. To prepare for future growth in the City of Broken Arrow and to help with redundancy and peak flow one additional Brine Tank will be added. This project is for the construction of one additional Brine Tank to the existing Verdigris River Water Treatment Plant and includes the associated site/civil, structural, electrical, and instrumentation and control improvements to support the proposed facility. HDR Engineering, Inc. designed these improvements. Construction time will be 365 calendar days.

This project was advertised on October 23rd and October 30th, 2025. An optional Pre-Bid Meeting was held virtually on November 4th, 2025, and an optional Site Visit Meeting was held on November 4th, 2025. There were two (2) bids received on November 13th, 2025. The Certified Bid Tabulation is attached. The lowest responsible bid was Crossland Heavy Contractor’s, Inc. for a Base Bid of $1,092,000.00.

 

Cost:                                                                $1,092,000.00

Funding Source:                     OWRB Loan

Requested By:                      Charlie Bright, P.E., Director of Engineering & Construction

Approved By:                      City Manager’s Office

Attachments:                                          Certified Bid Tabulation-VRWTP Brine Tank.Signed-2154350

 

Recommendation:

recommend

Award the lowest responsible bid to Crossland Heavy Contractor’s, Inc. and approve and authorize execution of a construction contract for the Verdigris River Water Treatment Plant On-Site Hypochlorite Generation System Brine Tank (Project No. 2154350)