Title: Approval of and authorization to execute Change Order #5 with Scissor Tail Construction for the Broken Arrow Public Safety Complex Fire Department Annex Building project (191711)
Attachments: 1. scan006247
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 05-19-2026

 

Title:

title

Approval of and authorization to execute Change Order #5 with Scissor Tail Construction for the Broken Arrow Public Safety Complex Fire Department Annex Building project (191711)

End

 

Background:

 The BAPSC Fire Department Annex Building project is to renovate the existing facility for the Fire Department. This project will add 7 Ambulance bays allowing for the quick resupply of all Ambulances throughout the City of Broken Arrow.    

Change Order #5 addresses the following additions/deletions/changes to the contract:

-                     This Change Order is to amend the Final Contract Price. The contract price due to previous change orders was $1,117,987.39. Crews performed additional sidewalk replacement on the northeast corner and adding additional conduit and plugs in the equipment room. Additionally the overrun for line item #4.

Total time added to contract is:

-                     0.

 

 The total cost for Change Order #5 amounts to $3,237.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $178,834.11

This Change Order(s):                                                               $3,237.00

Total Cost of Change Orders:                                          $182,071.11

Original Contract Amount:                                          $939,153.28

Revised Contract Amount:                                          $1,121,224.39

 

Percent Change in Contract:                                          19.39%

Applicable to Comp. Bid Act:                     13.37%

Cost:                                                                $3,237.00

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          BAPSC Reconciliatory Change order 5
 

Recommendation:

recommend

Approve and authorize execution of Change Order #5 with Scissor Tail Construction for the Broken Arrow Public Safety Complex Fire Department Annex Building project (191711)