title
Approval of final acceptance for the public improvements for Hartford Villas (sanitary sewer, water and paving)
End
Background:
Zimmerman Properties has completed the construction for the Hartford Villas. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements were constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvement includes the following: (1) Sanitary Sewer; (2) Water; (3) Paving.
The owner desires to donate the public improvements identified above to the City. These improvements have an approximate value of $133,822.50.
Cost: $0
Prepared By: Douglas L. Tiffany, P.E., Director of Engineering and Construction
Reviewed By: Finance Department
Assistant City Manager
Russell M. Gale, Acting City Manager
Approved By: Russell M. Gale, Acting City Manager
Attachments: Detailed Assessment Breakdown
Recommendation:
Staff recommends approving Final Acceptance and Donation of the Public Improvements: Sanitary Sewer, Water and Paving.