File #: 24-1276    Name:
Type: Consent Item Status: Agenda Ready
File created: 9/16/2024 In control: Broken Arrow City Council
On agenda: 10/15/2024 Final action:
Title: Approval of and authorization to execute Change Order No. 1 with Stronghand LLC for the Cedar Ridge Drainage Improvements (SW22050)
Attachments: 1. Final Change Order - Cedar Ridge Drainage Project 1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  10-15-2024

 

Title:

title

Approval of and authorization to execute Change Order No. 1 with Stronghand LLC for the Cedar Ridge Drainage Improvements (SW22050)

End

 

Background:

 The Cedar Ridge Drainage Improvements project was a Drainage Advisory project to correct an issue with a CMP pipe that was failing in the Cedar Ridge neighborhood.  The CMP was replaced with HDPE and a system that was not found in the survey was found during excavation.

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     The repair and replacement of an additional stormwater line. The line was not known during design. The line was rerouted to outfall in the correct area and an additional structure was placed.

-                     There is no change in contract time.

 

 The total cost for Change Order #1 amounts to $8,022.97

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $8,022.97

Total Cost of Change Orders:                                          $8,022.97

Original Contract Amount:                                          $81,750.88

Revised Contract Amount:                                          $89,773.85

 

Percent Change in Contract:                                          8.94%

Applicable to Comp. Bid Act:                     8.94%

Cost:                                                                $89,773.85

Funding Source:                     Stormwater Capital, Proposition 6

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Cedar Ridge Drainage Improvements Change Order 1 

 

Recommendation:

recommend

Approve and authorize execution of Change Order #1 with Stronghand, LLC for the Cedar Ridge Drainage Improvements (SW22050)