Acceptance of the Drainage Advisory Committee’s recommendation to expend 2018 Go Bond, Proposition 6 funds to construct an interceptor ditch and a storm sewer system to mitigate erosion along the north side of the Preserve Park Detention Pond (Case No. 24-008)
End
Background:
The proposed project is in northeast Broken Arrow just west of 37th St. The project will be to install an interceptor ditch, inlets, storm sewer pipes, repair the shore, and repair the asphalt path and other mitigation efforts at the Preserve Park Detention Pond.
Staff investigated the site and found that the north path is eroding and damaging the sidewalk. Staff also found that a berm that held back water from a wetland had been cut and the water flowed from the wetland also caused erosion issues.
Staff has designed plans for the mitigation and repair of these concerns.
The estimated construction cost to repair and mitigate is approximately $325,000.00 in 2024 Dollars.
This area flows to Adams Creek
On April 29, 2024, the Drainage Advisory Committee reviewed and recommended to City Council to approve the request for $325,000.00 in 2018 GO Bond Proposition 6 funds for the construction of an interceptor trench and a storm sewer system to mitigate erosion.
Cost: $325,000.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Charlie Bright, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Drainage Report, Exhibits
Recommendation:
recommend
Accept the Drainage Advisory Committees’ recommendation to expend 2018 GO Bond Proposition 6 funds to construct an interceptor ditch and storm sewer system to mitigate erosion along the north side of the Preserve Park Detention Pond.
end