Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of August 2023
End
Background:
In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the City’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the August 2023 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on September 15, 2023.
Over the course of the month of August 2023, the total wastewater collected, treated and discharged was 170.644 million gallons (MG). The average daily effluent flow was 5.066 MG.
This report will be updated on a monthly basis. Staff recommends the Authority acknowledge submittal of the Report.
Cost: None
Funding Source: None
Requested By: Charles Vokes, Utilities Director
Approved By: City Manager’s Office
Attachments: August Discharge Monitoring Report
August Monthly Operational Report
Recommendation:
recommend
Acknowledge submittal of the August 2023 Monthly Discharge Monitoring Report