Approval of and authorization to execute Change Order No. 1 with Mammoth Sports Construction LLC for the Nienhuis Park Synthetic Turf Fields project (2460360)
End
Background:
The Nienhuis Park Synthetic Turf fields project was to install turf on fields 1 and 4. This project included drainage so during heavy downpours the fields would not be flooded.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Remove and relocate existing scoreboards on fields 1 and 4. This includes new I beam for scoreboards, concrete around the bases, redo the electric and moving the electric lines from the field. The sod is also included
- 14 days of added time
The total cost for Change Order #1 amounts to $24,000
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $24,000
Total Cost of Change Orders: $24,000
Original Contract Amount: $1,560,739.20
Revised Contract Amount: $1,584,739.20
Percent Change in Contract: 1.54%
Applicable to Comp. Bid Act: 1.54%
Cost: $24,000
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Turf Fields Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Mammoth Sports Construction LLC for the Nienhuis Park Synthetic Turf Fields project (2460360)