The streets and stormwater roof replacement project is to completely replace the Streets and Stormwater building’s roof. The project has had several delays for material shipment, but the project is near completion. This CO will allow for the completion of the project.
Change Order No. 1 addresses the following additions/deletions/changes to the contract:
- Removal of original scuppers and cutting small section of the wall to raise scuppers to new roof level and install a TPO coated meal scupper with a close to match beauty ring on the outside of the building to match existing.
- There is no change in contract time.
The total cost for Change Order No. 1 amounts to $8,919.29
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $966.00
Total Cost of Change Orders: $966.00
Original Contract Amount: $278,772.00
Revised Contract Amount: $279,738.00
Percent Change in Contract: 0.35%
Applicable to Comp. Bid Act: 0%
Cost: $279,738.00
Funding Source: Sales Tax Capital Improvements
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office