Broken Arrow Municipal Authority
Meeting of: 08-04-2025
Title:
title
Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of June 2025
End
Background:
In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the City’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the June 2025 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on July 14, 2025.
Over the course of the month of June 2025, the total wastewater collected, treated and discharged was 268.613 million gallons (MG). The average daily effluent flow was 7.797 MG.
This report will be updated on a monthly basis. Staff recommends the Authority acknowledge submittal of the Report.
Cost: None
Funding Source: None
Requested By: Timothy S. Robins, PE, Utilities Department Director
Approved By: City Manager’s Office
Attachments: June Discharge Monitoring Report
June Monthly Operational Report
Recommendation:
recommend
Acknowledge submittal of the June 2025 Monthly Discharge Monitoring Report
end