Broken Arrow Municipal Authority
Meeting of: 08-03-2026
Title:
title
Approval of and authorization to execute Change Order #2 with Timber Wolf Excavating, LLC for the Oak Crest Addition Sanitary Sewer and Water Line Improvements project (S.23070)
End
Background:
The Oak Crest addition Sanitary Sewer and Water Line Improvements project is rehabilitating the aging infrastructure throughout that neighborhood.
Change Order #2 addresses the following additions/deletions/changes to the contract:
- Reconciliation of final quantities.
- There is a 0-day change in contract time.
The total cost for Change Order #2 amounts to $82,212.50
The additional cost associated with these changes is as follows:
Previous Change Orders: $61,228.40
This Change Order(s): $82,212.50
Total Cost of Change Orders: $143,440.90
Original Contract Amount: $6,860,730.00
Revised Contract Amount: $7,004,170.90
Percent Change in Contract: 2.09%
Applicable to Comp. Bid Act: 0.77%
Cost: $82,212.50
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: CO2 Oak Crest Addition Final Reconciliation
Recommendation:
recommend
Approve and authorize execution of Change Order #2 with Timberwolf Excavating, LLC for the Oak Crest Sanitary Sewer and Water Line Improvements Project (S.23070)