LEGISLATIVE RESEARCH CENTER
File #: 24-282    Name:
Type: Consent Item Status: Agenda Ready
File created: 2/15/2024 In control: Broken Arrow City Council
On agenda: 2/20/2024 Final action:
Title: Acceptance of the Drainage Advisory Committee's recommendation to expend 2018 Go Bond, Proposition 6 funds for retaining an engineering consultant to design a set of construction plans to mitigate erosion along Adams Creek adjacent to the Preserve Park Regional Detention Pond (Case No. 24-002)
Attachments: 1. 01-29-2024 Drainage Advisory Committee Minutes-draft, 2. 24-002 Packet
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 02/20/24

Title:
title
Acceptance of the Drainage Advisory Committee's recommendation to expend 2018 Go Bond, Proposition 6 funds for retaining an engineering consultant to design a set of construction plans to mitigate erosion along Adams Creek adjacent to the Preserve Park Regional Detention Pond (Case No. 24-002)
End

Background:
Erosion is occurring along the north bank of Adams Creek adjacent to Preserve Park Regional Detention Pond. The stream bank is eroding adjacent to the detention pond embankment.
Preserve Park Regional Detention Pond is located North of Albany St (61st St) and west of 37th St (209th St) immediately north of Adams Creek. The park and the pond are owned by the City of Broken Arrow. The regional detention pond was constructed in 2021. The area the regional detention pond serves is just under a square mile. The drainage area for Adams Creek at this point is approximately 7.5 square miles. The fully developed 1% (100-year) flow in Adams Creek is 10,582 cfs and the velocity is 9.7 ft/s. The fully developed 10% (10-year) flow in Adams Creek is 5,643 cfs and the velocity is 8.6 ft/s.
A 30-inch sanitary sewer runs parallel to the detention pond and along/through Adams Creek to the Adams Creek Northwest lift station. A portion of the steel casing over the line is exposed on the creek.
This area flows to Adams Creek.
On January 29, 2024, the Drainage Advisory Committee reviewed and recommended to City Council to approve the request for $50,000.00 in 2018 GO Bond Proposition 6 funds for obtaining a design consultant to design a set of construction plans to mitigate erosion along Adams Creek adjacent to the Preserve Park Regional Detention Facility.


Cost: $50,000.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Kenneth D. Schwab, Acting Director of Engineering and Construction
Approved By: City Manager's Office
Attachments: Drainage Report, Exhibits
...

Click here for full text