Broken Arrow City Council
Meeting of: 10-07-2025
Title:
title
Approval of and authorization to execute the Change Order No. 1 with Cherokee Pride Construction, Inc. for the Brentwood Drainage Improvements (2453170)
End
Background:
The Brentwood Drainage Improvements project was to improve the drainage by installing inlets in the street. This project also allowed the road to drain.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Additional quantity of concrete placement (Bid Item No 6). This is a quantity overrun that increased the overall cost of the contract.
- There is a 0 day change in contract time.
The total cost for Change Order #1 amounts to $6,210.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $6,2100.00
Total Cost of Change Orders: $6,210.00
Original Contract Amount: $72,650.00
Revised Contract Amount: $78,860.00
Percent Change in Contract: 8.55%
Applicable to Comp. Bid Act: 0%
Cost: $6,210.00
Funding Source: 2018 GO Bond and Street Sales Tax
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Brentwood Drainage Improvements Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Cherokee Pride Construction, Inc. for the Brentwood Drainage Improvements (2453170)
end