Broken Arrow Municipal Authority
Meeting of: 04-21-2026
Title:
title
Approval of and authorization to execute Change Order No. 1 with Cherokee Pride Construction, LLC for the Wagoner County Trunk Sewer project (22020)
End
Background:
The Wagoner County Trunk Sewer line project was to install brand new trunk sewer pipe through Events Park. The work was done in concurrence with the Events Park Infrastructure project. This line needed a bypass for 6 months due to a collapse of the existing line. The bypass allowed the project to continue and the continued use of the existing line while the new line was being constructed.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Bypass costs due to equipment, fuel and manhours
- Remobilization cost of the boring contractor
- Adding an additional manhole that was missed on the plans
- Lowering manholes under the existing road.
- Unbilled items deducted
Time Added to the contract:
- 45 days in added time.
The total cost for Change Order #1 amounts to $276,846.64
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $276,846.64
Total Cost of Change Orders: $276,846.64
Original Contract Amount: $3,441,442.00
Revised Contract Amount: $3,718,288.64
Percent Change in Contract: 8.04 %
Applicable to Comp. Bid Act: 8.04 %
Cost: $276,846.64
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Wagoner Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Cherokee Pride Construction, LLC for the Wagoner County Trunk Sewer project (22020).
end